South Africa2024-03-31en

INTEGRATED REPORT FOR THE YEAR ENDED 31 MARCH 2024

Summary

Eskom faces significant challenges with deteriorating plant availability, resulting in widespread loadshedding, increased operational costs, and mounting municipal debt, contributing to substantial financial losses. In response, Eskom is pursuing a strategic turnaround plan focused on operational and financial recovery, supported by a government debt relief program and the legal separation of its Transmission business. While losses were reduced to R25.5 billion and some reliability metrics improved, the overall situation remains critical with plant availability and loadshedding still major concerns.