Tampa Electric Company Polk Power Station Unit 2 Carbon Capture Permitting Matrix
Summary
Tampa Electric Company (TEC) has developed a comprehensive Permitting Matrix for its Carbon Capture System (CCS) Feed Study at Polk Power Station Unit 2, outlining federal, state, and local regulatory requirements. The FEED Study is scheduled from March 2023 to December 2026 (995 days), with overall project execution expected from October 2024 to December 2031 (1883 days). Key permitting processes include an estimated 24-month review for a Class VI Injection Well permit and 45-120 days for Section 404 dredge/fill permits. Construction is projected from September 2026 to July 2029 (740 days), followed by pre-commissioning and startup from July 2029 to December 2031 (640 days), indicating a multi-year project timeline.
Key Facts
Source Document
https://example-government.gov/policy-document-link
AI chat is part of Pro. See pricing →